Practical guide
Use the Islamabad–Rawalpindi grey structure BOQ to budget excavation, raft, reinforcement, masonry and labour. Start with the site levels and house configuration, then replace available allowances with measured quantities from your project.
Start with site levels and measured quantities
Enter the ground level below the road and check the formation level and excavation footprint. An 800 sq ft excavation footprint is a separate input from the total covered area over all floors. Review cushion and PCC blinding quantities before pricing raft concrete and reinforcement.
Read the reinforcement lines separately
The BOQ separates raft, columns and lintel-level tie beams from slab and supporting-beam steel. The slab and beam estimate uses a budgeting factor of 1.8 kg per sq ft of covered area. Use the approved bar bending schedule for procurement, including the required bar sizes and detailing.
Estimate a basement and check site exclusions
Enter the planned basement area. Check excavation, base slab, retaining walls, waterproofing and stairs against the drawings. Confirm working space, rock excavation, disposal, shoring and dewatering separately where applicable. Pile work is excluded.
Compare material rates and labour scope
Compare rates delivered to your plot, and ask which labour activities are included. Review the BOQ line by line with the contractor. Soil conditions, retaining works and contractor exclusions can make two houses with the same covered area cost different amounts.
Worked example
For a budgeting example, 1,600 sq ft × 1.8 kg/sq ft gives 2,880 kg for slabs and supporting beams. That figure covers those lines only. Compare the complete reinforcement scope against the drawings before placing an order.
Frequently asked questions
- Can I use one rate per square foot for every Islamabad house?
- Use that figure as a comparison after checking covered area and scope. Excavation, basement work and reinforcement allowances can vary with the project.
- What goes into the printable BOQ?
- The report lists selected items and prices. Review unpriced items and exclusions before using its subtotal to compare offers.